Q2 2026 QUARTERLY REPORT
28th
July 2026
• Construction of the Carpentaria Gas Plant made significant progress with key plant components
now installed on site. The project is tracking on schedule and on budget for a scheduled
commissioning in the fourth quarter of 2026
• Carpentaria-5H flow testing commenced in June, and was completed post quarter, achieving an
average rate over 30-days of 6.9 TJ / day (IP30) and an exit rate of 6.7 TJ / day, demonstrating a
remarkably low rate of decline
• The Birdum Creek 2D Seismic Survey acquisition commenced June, and was completed post
quarter, across the >20 TCF resource area in EP167 and EP168 to support future horizontal well
planning
• Successfully completed the $5.0 million Share Purchase Plan, complementing the $66.3 million
institutional Placement completed in April
• Territory Sands and Beetaloo Energy entered into long form loan documentation to support
development of the first in-basin frac sand operation
• Initial $2.5 million drawdown made under the $45 million Macquarie Midstream Infrastructure
Facility following satisfaction of all conditions precedent
• Total liquidity at end of the Quarter increased to $124.9 million, comprising $63.3 million in cash
and $61.5 million of undrawn funding available under the Macquarie facilities
Beetaloo Energy Australia Limited www.beetalooenergy.com 2
"The June 2026 quarter marked an important transition for Beetaloo Energy as we moved from planning
and funding into execution across our Beetaloo Basin portfolio. Construction of the Carpentaria Gas Plant
progressed during the quarter and remains on track for commissioning in the fourth quarter of 2026.
Commissioning of the plant will enable first pilot gas sales through connection of our existing Carpentaria
horizontal wells commencing this year.
We also continued to strengthen the foundations for future growth across the basin. The successful
completion of the Birdum Creek 2D Seismic Survey across our Western Permits has enhanced our
understanding of this highly prospective acreage and will support planning of future horizontal drilling
and stimulation programmes. The execution of long-form loan agreements with Territory Sands also
secured an important component of our long-term development supply chain.
Together, these achievements reflect the strong operational momentum across the business. We are
advancing the Carpentaria Pilot Project while continuing to unlock the broader potential of our portfolio,
all while maintaining a strong balance sheet and financial flexibility.
Encouraging performance from Carpentaria-5H has increased our confidence in the quality of the
resource and our development strategy as we continue to execute the Carpentaria Pilot Project and
create long-term value for shareholders. Activity across the wider Beetaloo Basin continues to accelerate
as operators progress appraisal and pilot development programmes, reinforcing confidence in the basin's
emergence as a strategically important new source of Australian gas supply. Beetaloo Energy is well
positioned to play a leading role in that development as we advance toward first pilot gas sales."
⎯ Alex Underwood, Managing Director
Beetaloo Energy Australia Limited www.beetalooenergy.com 3
NORTHERN TERRITORY OPERATIONS UPDATE
The June quarter marked a significant increase in operational activity across Beetaloo Energy's Northern
Territory assets following the end of the wet season. Multiple work programmes progressed in parallel,
including construction of the Carpentaria Gas Plant, completion of the Carpentaria-5H extended production
test, commencement of the Birdum Creek 2D Seismic Survey and continued development of the
infrastructure required to support first pilot gas production. These activities highlight the strong progress
made across the Company's Northern Territory operations during the quarter as the Carpentaria Pilot Project
continues to advance towards first pilot gas sales in Q4 2026.
Carpentaria Pilot Project Update
Significant progress was achieved during the quarter, with the key components of the Carpentaria Gas Plant
successfully mobilised to site and structural and mechanical installation works well advanced. Clearing for the
flowlines connecting the Carpentaria wells to the gas plant was completed, marking another important
milestone in the Pilot Project. The project continues to be executed safely and professionally, with no
reportable incidents, and remains on schedule and within budget.
Carpentaria-5H IP30 Flow Testing
Carpentaria-5H (“C-5H”) IP30 flow testing commenced on 11 June 2026 following prior periods of shut-in
and flowback. The well initially flowed at more than 14 TJ/day before quickly settling, achieving an average
30-day production rate of 6.9 TJ/day, following the end of the quarter and an exit rate of 6.7 TJ/day.
The low decline rates across multiple test periods supports the previously disclosed 2C recoverable gas
estimate of approximately 10 PJ at the well location1
and provided valuable reservoir and production
performance data to support future well planning and field development. Following testing, the well was
shut in and will be tied into the Carpentaria Gas Plant, alongside Carpentaria-2H and Carpentaria-3H, ahead
of pilot project gas sales following plant commissioning anticipated in Q4 2026.
Birdum Creek 2D Seismic Survey
Acquisition of the 236 kilometre Birdum Creek 2D Seismic Survey commenced mid-June and was completed
following the end of the quarter. The survey was undertaken over the > 20 TCF Gas Discovery Area in EP167
and EP168 and designed to support future horizontal drilling, improve reservoir characterisation and
maximise drilling opportunities.
The seismic processing is now underway with interpretation scheduled for Q3 2026.
1
NSAI Contingent and Prospective Resources announcement dated 29 May 2023
Beetaloo Energy Australia Limited www.beetalooenergy.com 4
OTHER CORPORATE NEWS
Research and Development and Midstream Infrastructure Facilities
No drawdowns were made under the Company's $30 million Research and Development Credit Facility
during the quarter. At 30 June 2026, $17.5 million remained available for drawdown under the facility.
During the quarter, the Company satisfied all conditions precedent under the $45 million Midstream
Infrastructure Facility and completed its initial drawdown of $2.5 million to support construction of the
Carpentaria Pilot Project. At 30 June 2026, $42.5 million remained available for drawdown.
Research and Development Tax Incentive
Following receipt of the FY2024 Research and Development Tax Incentive refund during the quarter, the
Company lodged its FY2025 Research and Development Tax Incentive application with AusIndustry. The
application has been registered and issued with a registration number.
The application relates to eligible research and development activities undertaken during the year ended 31
December 2025. The Company expects to lodge its FY2025 income tax return with the Australian Taxation
Office during July 2026, incorporating the FY2025 Research and Development Tax Incentive claim.
Territory Sands Project
During the quarter, the Company and Territory Sands Pty Ltd executed long-form loan agreements to fund
development of the Forest Hill South frac sand project, following execution of the binding term sheet
announced during the previous quarter. Initial loan funding commenced post quarter end.
The project is expected to establish a locally sourced supply of high-quality quartz sand for use as proppant
in hydraulic fracturing activities within the Beetaloo Basin. Development of a local supply chain is expected to
reduce logistics costs, improve security of supply and generate broader economic benefits for the Northern
Territory through local employment and engagement with regional communities.
Subsequent to quarter end, Territory Sands completed its first drawdown under the funding arrangements
announced by the Company, representing a further milestone in progressing development of the Forest Hill
South project.
Beetaloo Energy Tenements
Beetaloo Energy has included a schedule of its oil and gas leases in Appendix A as required under ASX
Listing Rule 5.4.3.
Beetaloo Energy Australia Limited www.beetalooenergy.com 5
COMMUNITY ENGAGEMENT
Darwin Raptors Ice Hockey Team
During the quarter, Beetaloo Energy was proud to continue its sponsorship of the Darwin Raptors ice hockey
team alongside Liberty Energy. Based at the Darwin Ice Skating Centre—the only ice rink in the Northern
Territory—the Raptors play an important role in promoting one of Australia's most unique sporting
communities. Our support reflects Beetaloo Energy's commitment to investing in local initiatives that bring
people together, encourage participation in sport and contribute to vibrant, connected communities across
the Territory. We congratulate the Raptors on another successful season and look forward to continuing our
partnership.
NT PETROLEUM SECTOR UPDATE
2nd April 2026: Tamboran Resources announced the Shenandoah South-6H average 20-day initial
production (IP20) flow rate of 10.3 million cubic feet per day (MMcf/day) from the 2,632 metre (8,635 foot)
horizontal section within the Velkerri Formation (B Shale)2
.
14th April 2026: Central Petroleum and its joint venture partners announced a new gas sale agreement
with the Northern Territory government that underwrites two new Palm Valley wells3
.
12th May 2026: Santos received Environment Management Plan approval from the NT Government for the
drilling and stimulation of up to 12 appraisal wells in the EP161 joint venture in the Beetaloo Basin. Santos is
planning to drill two wells in EP161 Q3 20264
.
29th May 2026: Tamboran Resources announced the completion of the acquisition of Falcon Oil & Gas
Limited5
.
2 Tamboran Resources announcement: SS-6H delivers average IP20 flow rate of 11.9 MMcf/d, normalized over 10,000 foot horizontal
dated 2 April 2026
3 Central Petroleum announcement: New Gas Sale Agreement underwrites two new Palm Valley wells dated 13 April 2026
4
Santos announcement: Second Quarter 2026 Report dated 23 July 2026
5
Tamboran Resources announcement: Tamboran completes acquisition of subsidiaries of Falcon Oil & Gas Ltd. 29 May 2026
Beetaloo Energy Australia Limited www.beetalooenergy.com 6
BALANCE SHEET AND LIQUIDITY
Beetaloo Energy’s cash balance at Quarter end was $63.3 million of which $62.2 million was held in Australian
dollars and US$0.8 million was held in United States dollars.
Beetaloo Energy’s total available liquidity at Quarter end was $124.9 million, comprising total cash of $63.3
million, $17.6 million undrawn under the R&D Facility, $42.5 million undrawn under the Midstream Facility
and $1.5 million undrawn under the Performance Bond Facility. All facilities are held with Macquarie Bank.
During the Quarter, 2,338,300 options were exercised at 24c per share, generating $561,192 in cash.
Payments to Related Parties of the Company and their Associates
Item 6.1: Appendix 5B description of payments to related parties of the Company:
Liquidity
Quarter Ended 30-Jun-26 31-Mar-26 31-Dec-25 30-Sep-25
Cash $63,252,905 $7,508,552 $17,956,969 $27,141,948
Debt 7
$(18,474,590) $(27,345,858) $(28,194,566) $(29,515,769)
Net Cash / (Debt)8
$44,778,315 $(19,837,306) $(10,237,597) $(2,373,821)
Production and Development Expenditure (ASX Listing Rule 5.2.1)
Beetaloo Energy did not incur production and development expenditure on its assets during the Quarter.
Exploration Expenditure (ASX Listing Rule 5.2.2)
Asset Nature of Expenditure Amount
Capitalised
EP187 Carpentaria Pilot Project $8,714,292
EP167/168 Birdum Creek 2D Seismic Survey $249,860
Total Capitalised $8,964,152
Expensed
EP187
Annual Licensing Fees (NT Government) $24,648
Consulting and Advisory Expenses $1,238,765
EP167, EP168,
(Western Beetaloo)
Annual Licensing and Administrative Fees
(NT Government and NLC)
$65,067
Consulting and Advisory Expenses $29,210
Total Expensed $1,357,690
Beetaloo did not incur exploration expenditure on its other assets during the Quarter.
6
Includes remuneration paid to the Managing Director and his spouse, Melissa Underwood, who transitioned from an arm’s
length consultancy agreement to employment as Head of Marketing in May 2026. Payments during the quarter also
included the Managing Director’s FY2025 Short-Term Incentive, settled partly in cash and partly in Restricted Rights.
7
Debt is comprised of $12,445,862 under Facility A (R&D Facility), $3,528,728 under Facility B (Performance Bond Facility) and
$2,500,000 under the Midstream Facility with Macquarie Bank Limited.
8
Net Cash / (Debt) is defined as cash minus debt for the purposes of this calculation.
Director Fees $21,000
Managing Director and Related Parties6
Remuneration $396,116
Total (Item 6.1) $417,116
Beetaloo Energy Australia Limited www.beetalooenergy.com 7
ABOUT BEETALOO ENERGY
Beetaloo Energy holds 28.9 million acres of highly prospective exploration tenements in the McArthur Basin
and Beetaloo Sub-basins, Northern Territory. Work undertaken by the Company since 2010 demonstrates
that the Eastern depositional Trough of the McArthur Basin, of which the Company holds around 80%, has
enormous conventional and unconventional hydrocarbon potential. The Beetaloo Basin, in which Beetaloo
Energy holds a substantial position, has world-class hydrocarbon volumes in place and a ramp up in industry
activity to appraise substantial discoveries already made by major Australian oil and gas operators is
ongoing.
THIS ASX RELEASE HAS BEEN AUTHORISED BY MANAGING DIRECTOR ALEX UNDERWOOD
Registered Office Beetaloo Energy Australia Limited
Level 5, 6-10 O’Connell Street ABN 29 002 148 361
Sydney NSW 2000
Phone: +61 2 9251 1846 Securities Exchange
ASX: BTL
Media and Investor Enquiries Share Registry
Nick Kell Computershare Investor Services
Phone +61 2 9251 1846 Phone: 1300 850 505
Beetaloo Energy Australia Limited www.beetalooenergy.com 8
APPENDIX A: INTEREST IN PETROLEUM PERMITS AND MINERAL TENEMENTS
Lease Holder Status Percentage of Interest Held
30 June 2026
EP180 Imperial Oil & Gas Pty Limited Application 100%
EP181 Imperial Oil & Gas Pty Limited Application 100%
EP182 Imperial Oil & Gas Pty Limited Application 100%
EP183 Imperial Oil & Gas Pty Limited Application 100%
EP184 Imperial Oi & Gas Granted 100%
EP187 Imperial Oil & Gas Pty Limited Granted 100%
EP188 Imperial Oil & Gas Pty Limited Application 100%
EP319 Imperial Oil & Gas Pty Limited Application 100%
EP320 Imperial Oil & Gas Pty Limited Application 100%
EP321 Imperial Oil & Gas Pty Limited Application 100%
EP322 Imperial Oil & Gas Pty Limited Application 100%
EP323 Imperial Oil & Gas Pty Limited Application 100%
EP324 Imperial Oil & Gas Pty Limited Application 100%
EP325 Imperial Oil & Gas Pty Limited Application 100%
EP326 Imperial Oil & Gas Pty Limited Application 100%
EP327 Imperial Oil & Gas Pty Limited Application 100%
EP328 Imperial Oil & Gas Pty Limited Application 100%
EP329 Imperial Oil & Gas Pty Limited Application 100%
EP330 Imperial Oil & Gas Pty Limited Application 100%
EP331 Imperial Oil & Gas Pty Limited Application 100%
EP332 Imperial Oil & Gas Pty Limited Application 100%
EP333 Imperial Oil & Gas Pty Limited Application 100%
EP334 Imperial Oil & Gas Pty Limited Application 100%
EP335 Imperial Oil & Gas Pty Limited Application 100%
EP336 Imperial Oil & Gas Pty Limited Application 100%
EP337 Imperial Oil & Gas Pty Limited Application 100%
EP338 Imperial Oil & Gas Pty Limited Application 100%
EP339 Imperial Oil & Gas Pty Limited Application 100%
EP340 Imperial Oil & Gas Pty Limited Application 100%
EP341 Imperial Oil & Gas Pty Limited Application 100%
EP342 Imperial Oil & Gas Pty Limited Application 100%
EP167 Imperial Oil & Gas A Pty Limited Granted 100%
EP168 Imperial Oil & Gas A Pty Limited Granted 100%
EP169 Imperial Oil & Gas A Pty Limited Granted 100%
EP198 Imperial Oil & Gas A Pty Limited Granted 100%
Share your feedback
Discover