“Following the end of the wet season, activity across the Beetaloo Basin has ramped up significantly as
we continue progressing towards pilot production from our Carpentaria Pilot Project.
Transportation of the Carpentaria Gas Plant and commencement of construction activities marks
another important milestone for the Company as we continue building out the infrastructure required
to support pilot production operations.
In parallel, preparations for the extended production test of Carpentaria-5H are nearing completion,
with flow testing expected to commence in the coming weeks.
At the same time, we are pleased to be advancing exploration activity in the Western Beetaloo, where
upcoming seismic acquisition is expected to further define the scale and quality of the resource
opportunity across this highly prospective area.
With multiple operational and exploration activities now underway, Beetaloo Energy is continuing to
build momentum across the basin as we execute our strategy to unlock the world-class potential of
the Beetaloo.”
Alex Underwood, Managing Director
BEETALOO ENERGY OPERATIONS UPDATE
11 June 2026
• All Carpentaria Pilot site civil works are complete, and installation of the Carpentaria Gas
Plant is ongoing
• The last two trucks carrying the second compressor unit and the intercooler are in transit
from Roma to the Carpentaria site. The Roma yard will be cleared and the lease returned
this month
• Gas gathering pipelines are being installed to connect C-2H, C-3H & C-5H to the
Carpentaria Gas Plant
• Carpentaria-5H Extended Production Test to commence mid-June
• Velseis to commence seismic acquisition in Western Beetaloo in late June to delineate
future drilling locations within the >20 TCF Western Beetaloo prospective resource area
Beetaloo Energy Australia Limited www.beetalooenergy.com 2
CARPENTARIA GAS PLANT
Beetaloo Energy is pleased to report that, following a long and intense wet season, the camp at the
Carpentaria Pilot Project reopened in May and work on the Carpentaria Gas Plant has ramped up.
The camp currently accommodates approximately 40 personnel working on gas plant construction. At
the time of writing the first compressor has been lifted into place and connecting pipe work is
progressing.
Construction of the gas gathering pipelines to link the gas plant to the three pilot wells is underway.
We look forward to updating shareholders as we progress.
Carpentaria Gas Plant site installation Intercooler loaded for Carpentaria
Beetaloo Energy Australia Limited www.beetalooenergy.com 3
Clean-up flow testing in late 2025 at Carpentaria 5H
CARPENTARIA 5H (C-5H)
Beetaloo Energy expects to recommence the extended production test of C-5H in mid-June subject to
final clean up. During clean-up flow testing operations in late 2025, C-5H achieved a peak gas flow rate
of 11.2 TJ/day and a 30-day average of 7.1 TJ/day with a day-30 exit rate of 6.3 TJ/day.
Installation of expanded water-handling infrastructure to manage water production is complete.
Beetaloo Energy Australia Limited www.beetalooenergy.com 4
WESTERN BEETALOO
A 2D seismic survey is planned to commence in June across the Gas Discovery Area between Tarlee S3
and Birdum Creek-1. The same reservoir units as Carpentaria will be targeted, but with significantly
thicker B Shale development.
Velseis Integrated Seismic Technologies Pty Limited will acquire ~230 km of seismic lines under existing
environmental approvals designed to optimise future horizontal well orientation.
Land access agreements have now been executed with pastoralists. Clearing for access will commence
in mid-June by local company Wildman River Stock Contractors.
The program is designed to delineate a >20 TCF resource and build a multi-decade LNG scale drilling
inventory strategically located near pipeline, road and rail infrastructure.
Seismic survey at Carpentaria EP187 in 2019 (Illustrative of the upcoming program)
Beetaloo Energy Australia Limited www.beetalooenergy.com 5
CORPORATE
As we progress towards pilot production, we continue to strengthen our team and are pleased to
welcome three new Darwin-based employees.
Damian Woods has joined as Operations Superintendent, with responsibility for the Carpentaria Project,
while Andrew Lewis and Audrey Santiaguel have joined the Environmental and Compliance team.
This ASX release has been authorised by the Managing Director, Alex Underwood
ABOUT BEETALOO ENERGY
Beetaloo Energy holds 28.9 million acres of highly prospective exploration tenements in the McArthur Basin
and Beetaloo Sub-basins, Northern Territory. Work undertaken by the Company since 2010 demonstrates
that the Eastern depositional Trough of the McArthur Basin, of which the Company holds around 80%, has
enormous conventional and unconventional hydrocarbon potential. The Beetaloo Basin, in which Beetaloo
Energy holds a substantial position, has world-class hydrocarbon volumes in place and a ramp up in industry
activity to appraise substantial discoveries already made by major Australian oil and gas operators is ongoing
Registered Office Beetaloo Energy Australia Limited
Level 5, 6-10 O’Connell Street ABN 29 002 148 361
Sydney NSW 2000
Phone: +61 2 9251 1846 Securities Exchange
Facsimile: +61 4 9251 1022 ASX: BTL
Media and Investor Enquiries Share Registry
Nick Kell Computershare Investor Services
Phone +61 2 9251 1846 Phone: 1300 850 505
Share your feedback
Discover