Quarterly Activities Report - 31 December
Released
Released
Announcement PDF
Beetaloo Energy Australia Limited T +61 2 9251 1846
ABN 29 002 148 361 info@beetalooenergy.com
Level 5, 6-10 O’Connell St, Sydney, NSW 2000
“The December Quarter marked a significant step forward for Beetaloo Energy as the Company progressed
toward pilot development and commercialisation. During the quarter, Federal Ministerial approval
recognising Traditional Owner consent for the sale of appraisal gas was secured, followed immediately by
NT Government approval of the Beneficial Use of Gas application, establishing a clear regulatory pathway
to gas sales from EP187.
The Board approved the Final Investment Decision (FID) for the Carpentaria Pilot Project, with first gas sales
from EP187 expected in 2026. This decision was supported by the strong performance of the Carpentaria-
5H well, which achieved one of the highest flow rates recorded in the Beetaloo Basin during flowback1
.
Permeability observed across the Carpentaria region indicates higher permeability than previously
assumed.
Beetaloo Energy enters the next quarter with key approvals in place, FID achieved, and a clear pathway
toward pilot production.
I would like to thank the Beetaloo Energy team along with our partners for their outstanding efforts
throughout the year, and our shareholders for their continued support and confidence in Beetaloo Energy.
Your commitment and trust have been instrumental as we advance our projects, and I look forward to
another year of progress and shared success”
⎯ Alex Underwood, Managing Director
Q4 2025 QUARTERLY REPORT
30th January 2026
• NT Government approved Beetaloo Energy’s Beneficial Use of Gas application for the sale of
appraisal gas from EP187
• Beetaloo Energy achieved a Final Investment Decision (FID) on the Carpentaria Pilot Project,
with first gas sales from EP187 expected in late 2026
• Civil works for the Carpentaria Gas Plant commenced in October 2025 and were completed in
January 2026. Piling installation will commence in February followed by gas compressor
transport to site in April
• Carpentaria-5H (“C-5H”) achieved strong flow rates with enhanced permeability, underpinning
long-term performance1
• Total liquidity at end of the Quarter was $24.8 million comprising $18.0 million in cash and $6.8
million of undrawn funding available under the Macquarie facilities. An additional $30 million
under the Macquarie Midstream Infrastructure Facility is expected to become available now that
FID has been reached
• Beetaloo Energy intends to recommence the C-5H flow in late Q1/early Q2
1
Beetaloo ASX Announcement dated 22 December 2025.
Beetaloo Energy Australia Limited www.beetalooenergy.com 2
NORTHERN TERRITORY OPERATIONS UPDATE
A 30-day clean-up flow test of the C-5H well was undertaken across November and December 2025. During
the test, the well achieved the second-highest 30-day average flow rate in the history of the basin of 7.1
TJ/day. A very low rate of decline was confirmed with an exit flowrate of 6.3 TJ/day2
.
Basin-leading flowback methodologies were implemented to preserve fracture conductivity and maximise
long-term well productivity. This approach utilised a restricted choke that extended the duration of clean-up,
however it delivered a greater than five-fold increase in fracture conductivity compared with the previous
Carpentaria wells.
Clean-up of the frac fluid from the fracture system was ongoing with the gas-to-water ratio continuing to
improve throughout the 30-day test period with over 23 percent of the frac fluid recovered at the time of
shut-in. Once frac fluid clean-up was achieved at the prior two Carpentaria wells, materially higher gas flow
rates were observed, with Carpentaria-3H recording a 30 percent increase in gas flow rate during the post
clean-up IP30 flow test.
Independent resource certifiers Netherland, Sewell & Associates have estimated 10 PJ recoverable gas per
well location of 2C resources in the Carpentaria-5H area3
. Based on flowback data analysis conducted by
Subsurface Dynamics, a North American shale reservoir engineering specialist, Beetaloo Energy estimates
that the Carpentaria-5H well has developed an effective fracture network, characterized by materially longer
fracture lengths relative to the previous two Carpentaria wells and higher apparent shale permeability in the
Carpentaria region. Beetaloo Energy believes these outcomes may support improved gas recovery and
overall project economics.
Following clean-up testing and shut-in late December 2025, wellhead pressure increased from ~283 psi to
the current pressure of ~1700 psi at the time of writing and continuing to rise.
2
Beetaloo ASX Announcement dated 22 December 2025.
3
Beetaloo ASX Announcement dated 29 May 2023.
Early works for the Carpentaria Gas Plant including clearing,earthworks and refurbishment of equipment in Roma commenced in early
October 2025 under an approved Environment Management Plan and with the consent of Traditional Owners
Beetaloo Energy Australia Limited www.beetalooenergy.com 3
Regulatory Approvals and Project Milestones`
During the quarter, Beetaloo Energy achieved a series of key regulatory and strategic milestones that
advance the Carpentaria Pilot Project and support the pathway to commercial gas production from EP187.
The Company received Federal and Northern Territory government approvals, including recognition of
Traditional Owner consent through the Northern Land Council and Ministerial approvals for the sale and
beneficial use of appraisal gas. These approvals mark important regulatory milestones, representing strong
support from Traditional Owners and government authorities and enabling the next phase of project
development.
Building on these approvals, the Board of Beetaloo Energy made a Final Investment Decision (FID) for the
Carpentaria Pilot Project. Achieving FID follows the receipt of all required environmental approvals,
agreement with Traditional Owners, the 2024 Gas Sales Agreement with the NT Government, and approval
for Beneficial Use of Test Gas. Collectively, these milestones provide a clear pathway for the Carpentaria Pilot
Project, including the construction of the Carpentaria Gas Plant, the commencement of gas sales and the
drilling and completion of up to 9 additional wells.
These regulatory achievements and the Board’s FID mark a defining step forward for Beetaloo Energy,
positioning the Company to progress toward pilot production and commercialisation, while continuing to
deliver long-term value for shareholders.
Following FID, $30 million of funding under the Macquarie Midstream Infrastructure Facility is expected to
become available to support gas plant construction.
Managing Director Alex Underwood and NT Minister for Mining & Energy Hon. Gerard Maley after The NT Government approved Beetaloo
Energy’s Beneficial Use of Gas application for sale of appraisal gas from EP187
Beetaloo Energy Australia Limited www.beetalooenergy.com 4
CARPENTARIA PILOT PROJECT UPDATE
Early works for the Carpentaria Gas Plant including clearing and earthworks were undertaken during the
quarter by Darwin based Top End Civil. This scope was completed in January 2026 with no recordable safety
or environmental incidents. Beetaloo Energy is excited to progress to the next stages of gas plant
construction which includes piling in February and moving the gas plant equipment, which is currently being
refurbished in Roma, to the Carpentaria site from April 2026.
The C-2H, 3H and 5H well pad is located approximately 5 kilometres from the Carpentaria Gas Plant site.
Gathering pipelines to connect the three existing wells to the compression facilities will be installed in Q2
followed by pressure testing. Beetaloo Energy anticipates early commissioning activities in Q3 2026
immediately followed by gas sales.
Carpentaria Gas Plant Site – looking north.
Beetaloo Energy Australia Limited www.beetalooenergy.com 5
OTHER CORPORATE NEWS
Research and Development Facility
During the quarter, no drawdowns were made under the $30 million R&D Facility with Macquarie Bank
Limited, as the Company had sufficient cash reserves to fund its operations.
The Midstream Infracstructure Facility is expected to become available for drawdown now that the compnay
has revieved Beneficial Use of Gas approval from the NT Government.
Beetaloo Energy Tenements
Beetaloo Energy has included a schedule of its oil and gas leases in Appendix A as required under ASX
Listing Rule 5.4.3.
Beetaloo Energy works closely with local communities and local businesses – Les Rice (Ricey’s Contracting) provides water truck services
on site for BTL.
Beetaloo Energy Australia Limited www.beetalooenergy.com 6
NT PETROLEUM SECTOR UPDATE
15th
October 2025: Tamboran completed the drilling of the Shenandoah-4H (SS-4H), -5H and -6H wells.
Each was cased with a target lateral length of 10,000 feet4
.
16th
October 2025: Santos announced that community engagement on the proposed Beetaloo Basin
Appraisal Environment Management Plan was completed during Q3 2025, along with consultation with
Traditional Owners on the proposed 2026 appraisal program. Concept studies for potential pipeline routes
connecting the Beetaloo Basin to Darwin and the East Coast market were also finalised5
.
12th
November 2025: Central Petroleum Limited announced that it has entered into a conditional sale and
purchase agreement to sell its interests in three Northern Territory sub-salt exploration permits - EP82,
EP112 and EP125 - to Georgina Energy Plc in consideration for a 25% equity interest in Georgina (amended
on 19 December to exclude EP82)6
.
15th
December 2025: Tamboran Resources successfully completed stimulation activities on the Shenandoah
South 6H (SS-6H) well, comprising 58 stages across a 10,009-foot (~3,050-metre) stimulated length in the
Mid Velkerri B Shale7
.
15th
December 2025: Mereenie and Palm Valley Joint Ventures agreed non-binding, conditional terms with
the Northern Territory’s Power and Water Corporation (PWC) for the sale of gas from the Mereenie and Palm
Valley fields through to the end of 20348
.
17th
December 2025: Santos announced completion of the divestment to Eni Australia of its 42.71% interest
in the Petrel fields and 100% in the Tern fields in the Bonaparte Basin offshore Northern Australia9
.
22nd
January 2026: Santos announced a drilling rig was secured during Q4 2025 for the Beetaloo Basin
program consisting of a 2-3 well campaign planned for the third quarter of 202610
.
4
Tamboran Resources ASX Announcement dated 15 October 2025
5
Santos Third Quarter Report (2025) dated 16 October 2025.
6
Central Petroleum ASX Announcement dated 21 November 2025.
7
Tamboran Resources ASX Announcement dated 15 December 2025
8
Central Petroleum ASX Announcement dated 15 December 2025.
9
Santos ASX Announcement dated 17 December 2025.
10
Santos Fourth Quarter Report (2025) dated 22 January 2025.
Beetaloo Energy Australia Limited www.beetalooenergy.com 7
BALANCE SHEET AND LIQUIDITY
Beetaloo Energy’s cash balance at Quarter end was $18.0 million of which $17.4 million was held in Australian
dollars and US$0.4 million was held in United States dollars.
Beetaloo Energy’s total available liquidity at Quarter end was $24.8 million, comprising total cash of $18.0
million, $4.6 million undrawn under the R&D Facility and $2.2 million undrawn under the Performance Bond
Facility. Both facilities are held with Macquarie Bank.
During the Quarter, 1,449,704 options were exercised at 24c per share, generating $347,929 in cash.
Following all regulatory approvals, Beetaloo Energy is expected to satisfy the conditions precedent to
drawdown of the $30 million Midstream Infrastructure Facility. Those funds will be applied to the
construction and installation of the Carpentaria Gas Plant and associated infield infrastructure.
Payments to Related Parties of the Company and their Associates
Item 6.1: Appendix 5B description of payments to related parties of the Company:
Liquidity
Quarter Ended 31-Dec-25 30-Sep-25 30-Jun-25 31-Mar-25
Cash (A$) $17,956,969 $27,141,948 $39,414,486 $14,396,319
Debt (A$)12
$(28,194,566) $(29,515,769) $(19,448,156) $(17,202,353)
Net Cash / (Debt)13
$(10,237,597) $(2,373,821) $19,966,330 $(2,806,034)
Production and Development Expenditure (ASX Listing Rule 5.2.1)
Beetaloo Energy did not incur production and development expenditure on its assets during the Quarter.
11
Managing Director remuneration includes his spouse, Melissa Underwood, who earns consulting fees under an arm’s length contract
approved by the Audit and Risk Committee of the Board
12
Debt is comprised of $25,445,340 under Facility A (R&D Facility), and $2,749,227 owing under Facility B (Performance Bond Facility) with Macquarie Bank
Limited
13
Net Cash / (Debt) is defined as cash minus debt for the purposes of this calculation
Director Fees $34,060
Managing Director and Related Parties11
Remuneration $211,135
Total (Item 6.1) $245,195
Beetaloo Energy Australia Limited www.beetalooenergy.com 8
Exploration Expenditure (ASX Listing Rule 5.2.2)
Asset Nature of Expenditure Amount
Capitalised
EP187 Carpentaria Pilot Project $6,464,920
Total Capitalised $6,464,920
Expensed
EP184 Annual Administrative fees (NLC) $6,065
EP187
Annual Licensing and Administrative fees
$256,524
(NT Government and NLC)
Consulting and advisory expenses $1,934,447
Total Expensed $2,197,036
Beetaloo did not incur exploration expenditure on its other assets during the Quarter.
Beetaloo Energy Australia Limited www.beetalooenergy.com 9
ABOUT BEETALOO ENERGY
Beetaloo Energy holds 28.9 million acres of highly prospective exploration tenements in the McArthur Basin
and Beetaloo Sub-basins, Northern Territory. Work undertaken by the Company since 2010 demonstrates
that the Eastern depositional Trough of the McArthur Basin, of which the Company holds around 80%, has
enormous conventional and unconventional hydrocarbon potential. The Beetaloo Basin, in which Beetaloo
Energy holds a substantial position, has world-class hydrocarbon volumes in place and a ramp up in industry
activity to appraise substantial discoveries already made by major Australian oil and gas operators is
ongoing.
This ASX release has been authorised by the Board of Directors.
Registered Office Beetaloo Energy Australia Limited
Level 5, 6-10 O’Connell Street ABN 29 002 148 361
Sydney NSW 2000
Phone: +61 2 9251 1846 Securities Exchange
Facsimile: +61 4 9251 1022 ASX: BTL
Media and Investor Enquiries Share Registry
Nick Kell Computershare Investor Services
Phone +61 2 9251 1846 Phone: 1300 850 505
Beetaloo Energy Australia Limited www.beetalooenergy.com 10
APPENDIX A: INTEREST IN PETROLEUM PERMITS AND MINERAL TENEMENTS
Lease Holder Status Percentage of Interest Held 31 December2025
EP180 Imperial Oil & Gas Application 100%
EP181 Imperial Oil & Gas Application 100%
EP182 Imperial Oil & Gas Application 100%
EP183 Imperial Oil & Gas Application 100%
EP184 Imperial Oi & Gas Granted 100%
EP187 Imperial Oil & Gas Granted 100%
EP188 Imperial Oil & Gas Application 100%
EP319 Imperial Oil & Gas Application 100%
EP320 Imperial Oil & Gas Application 100%
EP321 Imperial Oil & Gas Application 100%
EP322 Imperial Oil & Gas Application 100%
EP323 Imperial Oil & Gas Application 100%
EP324 Imperial Oil & Gas Application 100%
EP325 Imperial Oil & Gas Application 100%
EP326 Imperial Oil & Gas Application 100%
EP327 Imperial Oil & Gas Application 100%
EP328 Imperial Oil & Gas Application 100%
EP329 Imperial Oil & Gas Application 100%
EP330 Imperial Oil & Gas Application 100%
EP331 Imperial Oil & Gas Application 100%
EP332 Imperial Oil & Gas Application 100%
EP333 Imperial Oil & Gas Application 100%
EP334 Imperial Oil & Gas Application 100%
EP335 Imperial Oil & Gas Application 100%
EP336 Imperial Oil & Gas Application 100%
EP337 Imperial Oil & Gas Application 100%
EP338 Imperial Oil & Gas Application 100%
EP339 Imperial Oil & Gas Application 100%
EP340 Imperial Oil & Gas Application 100%
EP341 Imperial Oil & Gas Application 100%
EP342 Imperial Oil & Gas Application 100%
EP167 Imperial Oil and Gas A Granted 100%
EP168 Imperial Oil and Gas A Granted 100%
EP169 Imperial Oil and Gas A Granted 100%
EP198 Imperial Oil and Gas A Granted 100%
Beetaloo Energy Australia Limited www.beetalooenergy.com 11
APPENDIX B
Disclosures under ASX Listing Rule 5
ASX Listing Rule 5.30
(a) Name and type of well Carpentaria-5H, horizontal shale gas well
(b) Location of well and the details of the permit or
lease in which the well is located
Located in Beetaloo’s wholly owned and operated EP187 tenement, located
in the Beetaloo Sub-basin in the Northern Territory
(c) The entity’s working interest in the well Beetaloo holds a 100% working interest and operatorship in Carpentaria-5H
(d) If the gross pay thickness is reported for an interval
of conventional resources, the net pay thickness
N/A
(e) Geological rock type of the formation drilled The horizontal section has been drilled in the B Shale of the Velkerri Formation
(f) Depth of the zones tested The depths of the 2,955 metre (9,625 foot) fracture stimulated horizontal
section tested range from 1,626 to 1,595 metres (5,007 feet to 5,233 feet)
True Vertical Depth (TVD) referenced to Rotary Table (7.2 metres (23.6 feet)
above ground level). 2.955 metres (9,625 feet) of the 3,310 metres (10,860
feet) horizontal section was fracture stimulated.
(g) Types of test undertaken and the duration of the
tests
30-day initial clean-up gas flow test.
This 30-day clean-up gas flow test was preceded by ~33 days of stimulation
clean-up flow with gas breakthrough following the fracture stimulation
(h) The hydrocarbon phases recovered in the tests High Calorific Gas -
C-5H Gas recovery - mole %: Methane 82.77, Ethane 12.25, Propane 1.61,
Butane 0.34, Pentane and Higher 0.09.
Conversion factor of raw MMSCF to TJ is 1.173
(i) Any other recovery, such as , formation water and
water, associated with the test(s) and their respective
proportions
A total of 125,027 bbl of flowback fluid was recovered by the end of the 30-
day clean-up flowtest, including volumes from prior clean-up periods. This
represents 23.2% of total injected fluid. Over the 30-day period of measured
gas flow, fluid flowback declined from 2635 bbl/day to 677 bbl/day
(j) The choke size used, the flow rates and, if measured,
the volumes of the hydrocarbon phases measured
Choke adjustments from 62/64” to 88/64” over approximately the first two
and a half days of the 30-day clean-up test interval and maintained at 88/64”
to the end of the 30-days. Gas flow averaged 6.04 MMSCF / day (7.1 TJ/ day)
over the first 30 days. The Day 30 exit rate was 5.4 MMSCF / day (6.3 TJ /
day). Total gas flared during the 30-day clean-up flow test was 181.3 MMCF
(212.6 TJ)
(k) If flow rates were tested, information about the
pressures associated with the flow and the duration
of the test.
Wellhead pressure ranged from 659 psi to 283 psi during the 30-day clean-up
flow test period. The 30-day clean-up flow test commenced 20/11/2025 at 12
AM (ACST) and ended 20/12/2025 at 12 AM (ACST)
(l) The number of fracture stimulation stages and the
size and nature of fracture stimulation applied
67 slickwater stages along an effective stimulated horizontal length of 2,955
metres (9,695 feet) executed with a total of ~11,000 tonnes of proppant (sand)
placed representing an average proppant intensity of 2,295 lb/ft
(m) Any material volumes of non-hydrocarbon gases,
such as, carbon dioxide, nitrogen, hydrogen sulphide
and sulphur.
Mole %: Helium 0.14%, Carbon Dioxide 0.84% and other Inert volume 1.95%
(n) Any other information that is material to
understanding the reported results
Not applicable