30 June 2026 Half Year Financial Report
Released
Released
Announcement PDF
HALF-YEAR
FINANCIAL
REPORT
2026
Beetaloo Energy Australia Limited and its controlled entities
Contents
30 June 2026
1
Corporate directory 2
Chairman and Managing Director letters to Shareholders 3
Operations review 5
Directors' report 24
Auditor's independence declaration 28
Interim consolidated statement of profit or loss and other comprehensive income 29
Interim consolidated statement of financial position 30
Interim consolidated statement of changes in equity 31
Interim consolidated statement of cash flows 32
Notes to the interim consolidated financial statements 33
Directors' declaration 52
Independent auditor's review report to the members of Beetaloo Energy Australia Limited 53
Beetaloo Energy Australia Limited and its controlled entities
Corporate directory
30 June 2026
2
Directors Peter Cleary (Chairman)
Alexander Underwood (Managing Director)
Prof John Warburton
Karen Green
Company Secretary Sally McDow
Sally Greenwood
Registered office and principal
place of business Level 5, 6-10 O'Connell Street
Sydney NSW 2000
Share Registry Computershare Investors Services Pty Limited
Level 4, 44 Martin Place
Sydney NSW 2000
Auditor Ernst & Young
Level 34
200 George Street
Sydney NSW 2000
Australian Solicitors Baker McKenzie
Level 46, Tower One
International Towers Sydney
100 Barangaroo Avenue
Barangaroo NSW 2000
Ward Keller
Level 7 Northern Territory House
22 Mitchell Street
Darwin NT 0800
US Solicitors Hodgson Russ LLP
140 Pearl Street, Suite 100
Buffalo, NY 14202
Bankers Macquarie Bank Limited
1 Elizabeth Street
Sydney NSW 2000
Australia & New Zealand Banking Group Limited
1 Chifley Plaza
Sydney NSW 200
PNC Bank
249 Fifth Avenue
One PNC Plaza
Pittsburgh PA 15222
Stock exchange listing Beetaloo Energy Australia Limited shares are listed on the Australian
Securities Exchange (ASX code: BTL)
Website www.beetalooenergy.com
DearShareholders,
Thefirsthalfof2026hasbeenaperiodofsignificantprogressforBeetalooEnergyAustraliaLimited(“BeetalooEnergy”or“The
Company”)aswemovedfromplanningandfundingtoconstructionoftheCarpentariaPilotProject,whilecontinuingtoadvancethe
broaderpotentialofoursubstantialBeetalooBasinportfolio.
Atthebeginningoftheyear,ourprioritieswereclear:safelyandefficientlyprogressconstructionoftheCarpentariaGasPlant,further
demonstratetheproductivityofourresource,strengthentheCompany'sfinancialpositionandadvancetheCarpentariaPilotProject
towardsfirstpilotgassales.
Wehavemadesubstantialprogressagainsteachoftheseobjectives.
AdvancingtheCarpentariaPilotProject
FollowingFinalInvestmentDecisioninDecember2025,constructionoftheCarpentariaPilotProjectadvancedmateriallyduringthe
half-year.
RefurbishmentofkeycomponentsoftheCarpentariaGasPlantwascompletedinRomaandtheentireplantwastransportedtothe
Carpentariasite.By30June,structuralandmechanicalinstallationworkswerewelladvancedandclearingfortheflowlinesconnecting
theexistingCarpentariawellstothegasplanthadbeencompleted.Importantly,theprojectremainedonscheduleandwithinbudget,
withcommissioningtargetedforthefourthquarterof2026.
ThecommencementofpilotproductionwillrepresentamajormilestoneforBeetalooEnergy.Carpentaria-2H,Carpentaria-3Hand
Carpentaria-5Hareplannedtobeconnectedtothegasplant,providinganopportunitytoestablishlonger-termproduction
performanceandgeneratevaluablereservoirdatatoinformpotentialfuturedevelopmentoftheresourcewhilegeneratingourfirst
BeetalooBasincashflow.
Carpentaria-5H(“C-5H”)furtherdemonstratesresourcequality
DuringJune,wecommencedIP30flowtestingofC-5HfollowingtheendoftheNorthernTerritorywetseason.
Subsequenttohalf-yearend,testingwascompletedwithencouragingresults.C-5Hachievedapeakflowrateofmorethan14TJ/day,an
averageflowrateof6.9TJ/dayoverthe30-daytestperiodandanexitrateof6.7TJ/day.Thelowrateofdeclineobservedduringtesting
hasincreasedourconfidenceinthequalityoftheresourceandprovidesimportantproductionperformancedataasweprogressthe
CarpentariaPilotProject.
Strengthenedfinancialposition
Thehalf-yearalsorepresentedanimportantstrengtheningoftheCompany'sfinancialposition.InApril,wereceivedstrongsupport
fromexistingandnewinstitutionalandsophisticatedinvestorsfora$66.3millionplacement,whichwascomplementedbythe
successfulcompletionofa$5.0millionSharePurchasePlan.Thissupportfrombothinstitutionalandexistingshareholdersprovidesa
strongendorsementoftheCompany'sstrategyandtheopportunityrepresentedbyourBeetalooBasinassets.
TheCompanyalsoincreaseditsMacquarieBankMidstreamInfrastructureFacilityfrom$30millionto$45million.DuringtheJune
quarter,allconditionsprecedenttothefacilityweresatisfiedandaninitial$2.5millionwasdrawntosupportconstructionofthe
CarpentariaPilotProject.
Wealsoreceived$15.4million,includinginterest,undertheAustralianGovernment'sResearchandDevelopmentTaxIncentivein
respectofeligibleFY2024activities.
At30June2026,BeetalooEnergyhadtotalavailableliquidityofapproximately$124.9million,comprising$63.3millionofcashand$61.6
millionofundrawnfundingavailableundertheCompany'sMacquariefacilities.ThisfinancialpositionprovidestheCompanywith
substantialflexibilityasweexecutetheCarpentariaPilotProjectandprogressourbroaderportfolio.
BeetalooEnergyAustraliaLimited
ChairandManagingDirectorLettertoShareholders
30June2026
3
Buildingthefoundationsforfuturegrowth
WhiletheCarpentariaPilotProjectremainsourimmediateoperationalpriority,wecontinuedtoadvanceopportunitiesacrossour
broaderacreagepositionduringthehalf-yearwhilemaintainingstrongfinancialdiscipline.
Acquisitionofthe236-kilometreBirdumCreek2DSeismicSurveycommencedinJuneacrossthegreaterthan20TCFresourcearea
withinEP167andEP168andwascompletedsubsequenttohalf-yearend.Processingandinterpretationoftheseismicdatawillsupport
futurehorizontalwellplanning,improvereservoircharacterisationandassistinidentifyingfuturedrillingopportunitiesacrossour
WesternBeetalooacreage.
WealsocontinuedtoinvestinthedevelopmentofalocalBeetalooBasinsupplychain.Duringtheperiod,BeetalooEnergyandTerritory
SandsenteredintoaloanagreementtosupportdevelopmentoftheForestHillSouthfracsandproject.Establishinganin-basinsource
ofhigh-qualityfracsandhasthepotentialtosubstantiallyreducelogisticscostsandimprovesecurityofsupplywhilesupportinglocal
employmentandeconomicactivityintheNorthernTerritory.
BeetalooDigital–anopportunitytoleverageourBeetaloogasresource
Subsequenttotheendofthehalf-year,weannouncedtheestablishmentofBeetalooDigital,awhollyownedsubsidiarycreatedto
progressaproposedintegratedpoweranddatacentredevelopmentintheNorthernTerritory.
ThisinitiativerepresentsanexcitingpotentialnewpathwayforthedevelopmentandutilisationofourBeetalooBasingasresourceand
reflectsthegrowingdemandforreliable,dispatchableenergytosupportenergy-intensiveindustries.Theopportunityremainsatan
earlystageandissubjecttofurtherstudies,consortiumformationandthenecessarygovernmentandregulatoryapprovals.
TheestablishmentofBeetalooDigitaldoesnotchangeourimmediatepriority:successfulcommissioningoftheCarpentariaGasPlant
andcommencementofpilotgassales.Rather,itdemonstratestherangeoflonger-termopportunitiesthatmayemergeasthe
BeetalooBasinprogressestowardscommercialdevelopment.
Outlook
Theremainderof2026representsanimportantperiodforBeetalooEnergy.
Ourimmediatefocusisonthesafe,disciplinedandon-schedulecompletionandcommissioningoftheCarpentariaGasPlantandthe
commencementoffirstpilotgassales,currentlyanticipatedinthefourthquarterof2026.
Atthesametime,wewillcontinuetoprogressplanningforfutureappraisalactivityacrossourBeetalooBasinacreage,advanceourlocal
supplychaininitiativesandevaluateopportunitiesthatcansupportthelonger-termcommercialisationofoursubstantialresource
position.
InvestmentacrossthebroaderBeetalooBasincontinuestoaccelerateasoperatorsprogressappraisalandpilotdevelopmentprograms.
ThisincreasinginvestmentandactivityreinforceourconfidenceintheBasin'spotentialtoemergeasanimportantnewsourceof
Australiangassupply.
BeetalooEnergyentersthesecondhalfof2026withastrongbalancesheet,afullyfundedpathwaytofirstpilotgasproduction,
encouragingreservoirperformanceandsignificantoperationalmomentum.
Wethankourshareholdersandfinanciersfortheircontinuedsupport,ourTraditionalOwnerpartnersandNorthernTerritory
communitiesfortheirongoingengagement,governmentstakeholdersfortheirconstructivecollaboration,andouremployees,
contractorsandserviceprovidersfortheircommitmentandcontributionduringthisimportantperiodfortheCompany.Wealsothank
LouisRozman,whoretiredfromtheBoardduringthehalf-year,forhiscontributiontoBeetalooEnergyandwishhimwellforthefuture.
Yourssincerely,
PeterCleary
Chairman
BeetalooEnergyAustraliaLimited
AlexUnderwood
ManagingDirector
BeetalooEnergyAustraliaLimited
4
2026 HALF-YEAR
OPERATIONS REVIEW Forthesixmonthsended30June2026
2026 HALF-YEAR OVERVIEW & HIGHLIGHTS
Thefirsthalfof2026markedasignificanttransitionforBeetalooEnergyastheCarpentariaPilotProject(“CPP”)movedfrom
preparatoryworksintofullsiteinstallation,Carpentaria-5H(“C-5H”)inEP187returnedtoextendedflowtestingandfield
activitycommencedintheWesternBeetaloopermits.Theperiodalsoincludedmaterialprogressinlocalsupply-chain
developmentandfundingofthePilotProjectthroughtofirstgas.
CarpentariaGasPlantsiteinstallation
5
H1 2026 AT A GLANCE
Carpentaria Gas Plant civil works and piling completed, with refurbishment in Roma completed and key
plant components mobilised to the Carpentaria site.
Structural and mechanical installation of the Carpentaria Gas Plant well advanced by 30 June 2026; gas
gathering flowline clearing completed.
C-5H extended production testing commenced on 11 June 2026, with an initial rate of >14 TJ/day and
encouraging low decline observed through period end.
First pilot gas sales remain targeted for Q4 2026 following commissioning of the Carpentaria Gas Plant.
Birdum Creek 2D Seismic Survey commenced in June across EP167 and EP168 in the Western Beetaloo.
Long-form documentation completed with Territory Sands to support development of an in-basin
fracture stimulation sand mine near Larrimah.
Carpentaria Pilot Project activities continued without reportable environmental, health or safety incidents
during the period.
$66.3 million institutional placement completed in April 2026, strengthening the Company’s funding
position to advance the Carpentaria Pilot Project and broader Beetaloo work programs.
$15.4 million FY2024 R&D Tax Incentive refund received in April 2026, supporting execution of the Pilot
Project and ongoing appraisal activities.
6
OVERVIEW
Beetaloo Energy is an Australian upstream petroleum company focused on the appraisal and development of
large-scale unconventional shale gas resources in the Northern Territory. The Company holds a 100%
working interest across its core Beetaloo Basin acreage, including the Carpentaria Project in EP187 and the
Western Beetaloo permits EP167 and EP168.
During the six months ended 30 June 2026, the Company’s principal operational focus was execution of the
CPP and progression towards first pilot gas sales. Following Final Investment Decision in December 2025,
activity advanced across gas plant construction, well testing and infield infrastructure, while appraisal
activity commenced across the Western Beetaloo permits.
The CPP is designed to connect the existing Carpentaria-2H (“C-2H”), Carpentaria-3H (“C-3H”) and C-5H
wells to the 25 TJ/day CPP. In addition to supplying appraisal gas to the Northern Territory market, the project
is intended to generate longer-term production and reservoir performance data to inform future
development decisions.
Beetaloo Energy Acreage / Access to gas markets map
7
BEETALOO ENERGY’S STRATEGIC ASSETS
Beetaloo Energy’s portfolio comprises two core areas in the Beetaloo Basin: Carpentaria (EP187) and the
Western Beetaloo (EP167 and EP168). Together, these assets provide a large and strategically positioned
acreage base within one of Australia’s most prospective emerging onshore gas basins.
The CPP remained the Company’s primary operational focus during H1 2026. Work progressed across the gas
plant, gas gathering infrastructure and C-5H extended production testing as the Company advanced
towards pilot production.
In the Western Beetaloo, the Company commenced its first on-ground field program since acquiring EP167
and EP168 in 2021, with the Birdum Creek 2D Seismic Survey commencing in June 2026. The program is
designed to improve reservoir characterisation and support selection of future horizontal drilling locations
across the >20 TCF Gas Discovery Area.
Strategic Assets Map - Carpentaria and Western Beetaloo
8
CGP
CARPENTARIA WORKS TO DATE
The vertical Carpentaria-1 well established the
presence and productivity of the Velkerri
Formation shales. Subsequent appraisal wells,
Carpentaria-2 and Carpentaria-4V
demonstrated lateral continuity across the
permit and generated technical knowledge
regarding drilling and stimulation techniques
applicable to the Basin.
Horizontal wells C-2H, C-3H and C-5H have
further advanced understanding of reservoir
performance and completion design. The
record-scale C-5H stimulation program
completed in July 2025 applied a 2,955 metre
stimulation across 67 stages and approximately
11,000 tonnes of proppant, providing the
foundation for the extended production testing
undertaken in 2026.
The CPP represents the next phase of appraisal,
with the three existing horizontal wells planned
to be tied into the CGP to enable longer-term
production, gas sales, and reservoir
performance monitoring than is possible
through short-duration flaring tests.
Since commencing on-ground activity in 2019, Beetaloo Energy has progressively appraised the
stacked shales of the Velkerri Formation in EP187 through seismic acquisition, vertical and
horizontal drilling, hydraulic stimulation and production testing.
Carpentaria Gas Project - Velkerri B Shale Depth Map
9
INITIAL RATE
>14
TJ/DAY
Initial gas rate
IP30 AVERAGE RATE
6.9
TJ/DAY
30-day average flow rate
EXIT RATE
6.7
TJ/DAY
Exit rate
C-5H is estimated to contain approximately 10 PJ of recoverable gas with sub 1% CO
2
at the well location1. Longer-term production data is required to assess connected
reservoir volume and ultimate well productivity.
Following completion of testing, C-5H was shut in and is planned to be tied into the
Carpentaria Gas Plant alongside C
-2H and C-3H ahead of pilot gas sales.
CARPENTARIA-5H EXTENDED PRODUCTION TEST
Following the 2025 clean-up flow test and the Northern Territory wet season, C-5H was reopened
on 11 June 2026 for extended production testing, with 30-day (IP30) results announced
following the half-year end. The test was designed to continue well clean-up, obtain additional
reservoir and production performance data and improve understanding of longer-term well
behaviour.
C-5H was opened at an initial gas rate of >14 TJ/day and over the 30-day test period had an
average flow rate of 6.9 TJ/day and an exit rate of 6.7 TJ/day.
The well exhibited a low gas decline rate during the testing, with water rates substantially
declining as the well continued to clean up. Throughout the phases of testing, management
remained confident in the previously disclosed recoverable gas estimate of approximately 10 PJ,
with sub 1% CO , at the C-5H well location[1], whilst recognising that longer-term production
data is required to assess connected reservoir volume and ultimate well productivity.
2
Following completion of testing, C-5H was shut in and is planned to be tied into the Carpentaria
Gas Plant alongside C-2H and C-3H ahead of pilot gas sales.
[1] NSAI Contingent and Prospective Resources announcement dated 29 May 2023
10
C-5H is estimated to contain approximately 10 PJ of recoverable gas with sub 1% CO₂
at the well location. Longer-term production data is required to assess connected
reservoir volume and ultimate well productivity.
WORKSTREAM STATUS H
1 2026
1 Civil Works Complete
2 Piling Complete
3 Plant Refurbishment Complete
4 Plant Transport Complete
5 Mechanical Installation Advanced
6 Flowlines Cleared
7 Commissioning Upcoming
8 Gas Sales Q4 2026
CARPENTARIA PILOT PROJECT -
INFRASTRUCTURE PROGRESS
Significant progress was made on the Carpentaria Pilot Project during H1 2026. Civil works for the Carpentaria
Gas Plant were completed in January and piling of the structural foundations progressed before an unusually
heavy Northern Territory wet season temporarily restricted heavy vehicle access to site.
Offsite refurbishment and planned modifications to the gas plant equipment in Roma were completed, with
refurbishment works completed under budget. Following improvement in site access, transportation of the
plant components to Carpentaria commenced in April 2026.
By 30 June 2026, the key components of the Carpentaria Gas Plant had been mobilised to site and structural
and mechanical installation works were substantially progressed. Clearing for the gas gathering flowlines
connecting C-2H, C-3H and C-5H to the plant had also been completed.
The project continued to be executed safely and professionally, with no reportable environmental, health or
safety incidents, and remained on schedule and within budget. Commissioning and commencement of pilot
gas sales remain targeted for Q4 2026.
WORKSTREAM STATUS H1 2026
11
Construction works at the Carpentaria Gas Plant
Construction works at
the Carpentaria Gas Plant
12
WESTERN BEETALOO - EP167 AND EP168
Beetaloo Energy acquired the Western Beetaloo permits in 2021 and received Environment Management
Plan approval for exploration and appraisal activities in 2024. The area contains a large gas resource and
benefits from proximity to existing road, rail and gas pipeline infrastructure.
During H1 2026, the Company progressed planning and contracting for the Birdum Creek 2D Seismic Survey.
Acquisition commenced in mid-June across the deeper eastern portion of the Gas Discovery Area in EP167
and EP168, representing the first on-ground field program since the permits were acquired.
The approximately 236-kilometre survey was designed to improve the existing seismic grid across the
resource area, support future horizontal drilling, improve reservoir characterisation and maximise potential
drilling locations. The program targets the same prospective Velkerri Formation intervals as the Carpentaria
Project, including an area where the Velkerri B Shale is materially thicker. Acquisition of the Birdum Creek 2D
Seismic Survey was completed after 30 June 2026. Processing and interpretation of the seismic data is
underway, with interpretation scheduled during Q3 2026 to support planning of future appraisal drilling
activities.
Western Beetaloo Map with Birdum Creek 2D seismic survey lines
13
TERRITORY SANDS - LOCAL SUPPLY CHAIN
DEVELOPMENT
During the half-year, Beetaloo Energy progressed an agreement with Territory Sands to support
development of an in-basin frac sand mining project near Larrimah in the Northern Territory.
Long-form loan documentation was completed under which Beetaloo Energy will provide $10.4 million to
fund construction and commissioning of the project. Under the agreement, Beetaloo Energy will have
priority access to fracture stimulation sand supply from the mine at market competitive pricing.
A local source of suitable fracture stimulation sand has the potential to reduce transport distances and
supply costs for future stimulation campaigns, improve security of supply and support development of a
local Beetaloo Basin service and supply chain. The project also has the potential to support future activity by
other operators across the Basin.
SECURITY AND QUALITY OF SUPPLY
LOCAL ECONOMIC BENEFIT
REDUCED TRANSPORT DISTANCE
14
Carpentaria Gas Plant
RESEARCH & DEVELOPMENT
Beetaloo Energy’s appraisal activities continue to involve applied R&D focused on adapting horizontal drilling,
hydraulic stimulation, testing and analytical techniques to the ancient shales of the Beetaloo Basin.
In April 2026, the Company received a cash refund of $15.4 million, including interest, under the Australian
Government’s Research and Development Tax Incentive for eligible activities undertaken during the year
ended 31 December 2024. Eligible activities related primarily to horizontal drilling and hydraulic stimulation
processes, new testing and analytical processes for ancient shales and technical work supporting the
Carpentaria Pilot Project.
The refund strengthened the Company’s funding position and supported continued execution of the
Carpentaria Pilot Project, C-5H flow testing and progression towards pilot gas production.
15
HEALTH, SAFETY AND ENVIRONMENT
Health, safety and environmental management remained a core focus throughout the first half of 2026. The
CPP civil works, piling, gas plant transportation and installation activities, together with C-5H flow testing
and commencement of the Western Beetaloo seismic program, were undertaken under approved
Environment Management Plans and applicable regulatory requirements.
The Company managed one of the heaviest Top End wet seasons experienced in several decades by safely
demobilising crews and restricting access when conditions were unsuitable for heavy vehicles. Activities
recommenced progressively as access conditions improved.
CPP construction continued without reportable environmental, health or safety incidents during the period.
The Company remains focused on maintaining strong safety and environmental performance as activity
increases towards commissioning and pilot production.
Installation of foundation piles at Carpentaria Gas Plant
16
H1 2026 WRAP UP
The first half of 2026 represented a significant execution period for Beetaloo Energy as the Company
progressed the CPP towards first pilot gas sales. Despite a prolonged and intense wet season, civil and piling
works were completed, the CGP was refurbished and transported to site, installation advanced and the
infrastructure required to connect the three pilot wells progressed.
C-5H returned to extended production testing in June and delivered encouraging low-decline performance,
with the completed IP30 result announced shortly after half-year end. The test provides important
additional reservoir and production data ahead of the well being tied into the Pilot Project.
At the same time, commencement of the Birdum Creek 2D Seismic Survey marked the start of a new phase
of appraisal across the Western Beetaloo, while the Territory Sands agreement progressed development of a
local supply chain capable of supporting future stimulation activity across the Basin.
The Company’s near-term operational focus remains the safe and disciplined completion and commissioning
of the Carpentaria Gas Plant and commencement of pilot gas sales in Q4 2026. Longer-term production data
from the Pilot Project, together with interpretation of the Western Beetaloo seismic program, will inform
future appraisal and development planning across the Company’s substantial resource position.
17
The Group has a $80 million credit facility with Macquarie Bank Limited (“Macquarie”) to support its activities
in the Northern Territory. The outstanding balance of the credit facility as at 30 June 2026 is $18.4 million
(made up of $12.4 million of the R&D Facility, $2.5 million of the Midstream Facility and $3.5 million of the
Performance Bond facility).
Key terms of this credit facility are set out below:
Principal amount $80 million comprising:
- Facility A (R&D Facility, $30.0 million)
- Facility B (Performance Bond Facility, $5 million)
- Facility C (Midstream Infrastructure Facility, $45 million)
Borrowers Imperial Oil & Gas Pty Limited
Imperial Oil & Gas A Pty Limited
Guarantor Beetaloo Energy Australia Limited,
Imperial Oil & Gas Pty Limited and
Imperial Oil & Gas A Pty Limited
Security - First ranking security over assets of each Borrower
- First ranking security over the Guarantor’s shares in each Borrowings and
intercompany loans, plus featherweight security over the Guarantor’s
other assets
Fees - Utilisation Fee (Facility A): 1.5% of utilisation
- Commitment Fee (Facility A and B): 40% of margin
- Margin (Facility A): (5.5% p.a.), Facility B (10% p.a.)
- Tolling Fee (Facility C): F × 25 TJ/day × CPI, where F steps from A$0.70/GJ
(total Utilisations ≤ A$30 million) to A$1.05/GJ (total Utilisations = A$45
million); for drawdowns between A$30 million and A$45 million,
F = A$0.70 + (0.35 × (total Utilisations − A$30 million) ÷ A$15 million) per GJ.
Interest rate Margin plus BBSW (Facility A)
Financial covenants - Ratio of current assets to current liabilities of at least 1.00 to 1.00
- Minimum cash balance in the Borrowers and Guarantor of at least $10
million (or its equivalent in any other currency or currencies)
Repayment date 30 December 2026 (Facility A + B)
31 December 2034 (Facility C)
CREDIT FACILITIES
18
Repayment arrangements Facility A: on receipt of relevant annual R&D Tax Incentive payment
Facility B: on maturity date
Facility C: Beetaloo Energy may elect to prepay the Midstream
Infrastructure Facility at any time by making payment of an amount
representing a 15% IRR for the Midstream Infrastructure Facility
cashflows up to the date of prepayment including all tolls paid up to
the date of prepayment
Conditions precedent to first - All regulatory and indigenous approvals in place to allow for sale of
utilisation (Facility C) gas from the Carpentaria Pilot Project under the Beneficial Use of
Test Gas provisions of the NT Petroleum Act
- C-5H to be drilled to a lateral length of at least 2,700 metres with
at least 50 fracture stimulation stages placed
- Evidence of funding for the Carpentaria Gas Plant exceeding costs
to complete
- Issue of the Options to Macquarie
- All conditions were satisfied by 30 June 2026
Options - Beetaloo Energy issued 75 million options to Macquarie on 21 May
2026 in connection with the R&D Facility and Midstream
Infrastructure Facility, comprising Tranche A Options with an
exercise price of $0.24, Tranche B with an exercise price of $0.28
and Tranche C with an exercise price of $0.35. The options expire on
31 December 2029.
19
BUSINESS RISK
The material business risks that could adversely affect the Group’s financial performance and growth
potential in future years and how the Group proposes to mitigate such risks were detailed in the Annual
Report at 31 December 2025. Those risks have been assessed up to the reporting date with no significant
changes noted since then.
Exploration risk – Beetaloo Energy and its subsidiaries have interests in assets at various stages of
exploration, appraisal and development. Many leases have had very low levels of exploration undertaken to
date and may not yield commercial quantities of hydrocarbons. Oil and gas exploration is inherently subject
to numerous risks, including the risk that drilling will not result in commercially viable oil and gas production.
Beetaloo Energy utilises well-established prospect evaluation and ranking methodology to manage
exploration risks.
Application risk – Several of Beetaloo Energy’s Northern Territory assets are in the application stage
requiring native title and / or regulatory approvals to be granted as leases capable of being explored on. Such
approvals may or may not be granted which could adversely impact the value of the Company.
Regulatory risk – Beetaloo Energy has operations in the Northern Territory, Australia, where exploration,
appraisal, development and production activities are subject to regulatory approvals from the relevant
authorities. The granting, retention and renewal of these approvals are determined by external regulators
and are, ultimately, not within the Company’s control. There is a risk that approvals currently in place may be
amended, suspended or revoked, and that approvals required for future activities may not be granted, may
be delayed, or may be subject to conditions that could impact project viability and, therefore, the financial
performance of the Company.
Debt facility risk – Beetaloo Energy, through its subsidiaries, has a debt facility in place with Macquarie Bank
Limited. Whilst Beetaloo Energy has financial flexibility and expects to repay its debts in full, there is a risk in
the future that financial and other covenants under the debt facilities could be breached, which could result
in Macquarie exercising its security rights under the facilities.
Commodity price risk – Beetaloo Energy, through its Australian subsidiary, explores for oil and gas in
Australia and may be subject to domestic Australian gas price risk, LNG price risk and oil price risk. The gas
sales agreement between Beetaloo Energy and the Northern Territory Government is a fixed price, 100% CPI,
take-or-pay contract meaning that Beetaloo Energy is not exposed to commodity price risk for these
volumes.
20
BUSINESS RISK
Reliance on Key Personnel – The Company’s success depends on retaining key executives, technical staff
and operations personnel. Rapid organisational growth increases pressure on capability retention. Loss of key
individuals could adversely impact performance and execution of the Company’s growth plans.
Furthermore, the industry in which Beetaloo Energy operates faces challenges in attracting and retaining
personnel with specialised skills and expertise. The inability to attract and retain such individuals could
potentially disrupt business continuity through the loss of critical capability. To address this risk, Beetaloo
Energy has implemented employment arrangements that are specifically designed to secure and retain key
personnel.
Economic risk – General economic conditions, movements in interest rates, inflation rates and foreign
exchange rates, investor sentiment, demand for, and supply of capital and other general economic
conditions may have a negative impact on Beetaloo Energy and its subsidiaries’ ability to carry out its
exploration, appraisal, development and production plans.
Social Licence to Operate – Beetaloo Energy’s business performance is founded on maintaining a strong
social licence to operate, which is dependent on full compliance with applicable laws and regulations, as well
as upholding high standards of ethic