Carpentaria-5H IP30 flow test results
Released
Released
Announcement PDF
Beetaloo Energy Australia Limited T +61 2 9251 1846
ABN 29 002 148 361 info@beetalooenergy.com
Level 5, 6-10 O’Connell St, Sydney, NSW 2000
“The C-5H results are another important milestone for Beetaloo Energy as we continue our transition
from an exploration and appraisal company to a gas producer. The well has now delivered stable
production performance across an extended testing period, providing further confidence in the
quality of the Velkerri Shale at Carpentaria. Importantly, C-5H continued to demonstrate strong and
consistent gas rates during clean-up, highlighting the quality of the reservoir and supporting our
previously estimated recoverable gas resource at the well location. As we move closer to
commissioning the Carpentaria Gas Plant and achieving first gas sales from the Pilot Project, we are
increasingly focused on converting this resource opportunity into long-term value for shareholders.”
⎯ Alex Underwood, Managing Director
Carpentaria-5H IP30 Flow Test
13 July 2026
• Carpentaria-5H (“C-5H”) IP30 flow testing is complete, achieving a peak rate of
>14 TJ / day, an average rate over the 30-days testing of 6.9 TJ / day (IP30) and an exit rate
of 6.7 TJ / day.
• A sustained production profile was maintained across the entire C-5H testing program, as
demonstrated by latest exit rate of 6.7 TJ / day compared to the exit rate of the previous
test of 6.3 TJ / day. This supports the potential long-term gas deliverability of the resource.
• The C-5H well is currently shut-in and will be tied in for production along with the
Carpentaria-2H and Carpentaria-3H wells.
Carpentaria-5H flare during testing
Beetaloo Energy Australia Limited www.beetalooenergy.com 2
CARPENTARIA-5H (C-5H)
As previously announced, IP30 flow testing commenced on 11 June 2026. The well opened with an
initial gas rate of >14 TJ / day before settling to an average 30-day (IP30) rate of 6.9 TJ / day. The well
exhibited a low rate of decline over the 30 days of testing, with an exit flow rate of 6.7 TJ / day.
Since completion of the C-5H hydraulic stimulation in July 2025, the well has demonstrated a
progressive clean-up through the successive flowback and production testing campaigns. During this
IP30 production period, water production declined significantly from approximately 1,300 barrels per
day to around 440 barrels per day and continued to decrease throughout the test. The extended clean-
up period reflects the substantially larger completion design of Carpentaria-5H (“C-5H”), which
incorporates a longer lateral section and approximately twice the stimulation fluid intensity of the
earlier Carpentaria-2H (“C-2H”) and Carpentaria-3H (“C-3H”) wells, necessitating a longer-duration and
higher-volume flowback programme. C-5H water rates remain higher than C-2H and C-3H exit rates
indicating that some clean-up is still ongoing.
Beetaloo Energy previously reported a 30-day clean-up production rate averaging 7.1 TJ / day, with an
exit rate of 6.3 TJ / day, achieved using a larger choke setting than that used during the current IP30
production test. Across the two consecutive 30-day periods, the average production and exit rates were
very similar, demonstrating stable and consistent performance. This further supports the previously
disclosed recoverable gas (2C) estimate of approximately 10 PJ for the C-5H well location1.
This extended production test has delivered valuable production and reservoir performance data that
will inform future development activities and underpin Beetaloo Energy’s transition from an exploration
and appraisal company to a gas producer.
Following the extended production testing, the well has been shut in. With the anticipated
commissioning of the Carpentaria Gas Plant in the fourth quarter 2026, the C-2H, C-3H and C-5H well
will now be tied in for production for Pilot Project first gas sales.
1
NSAI Contingent and Prospective Resources announcement dated 29 May 2023
Beetaloo Energy Australia Limited www.beetalooenergy.com 3
ABOUT BEETALOO ENERGY
Beetaloo Energy holds 28.9 million acres of highly prospective exploration tenements in the McArthur Basin
and Beetaloo Sub-basins, Northern Territory. Work undertaken by the Company since 2010 demonstrates
that the Eastern depositional Trough of the McArthur Basin, of which the Company holds around 80%, has
enormous conventional and unconventional hydrocarbon potential. The Beetaloo Basin, in which Beetaloo
Energy holds a substantial position, has world-class hydrocarbon volumes in place and a ramp up in industry
activity to appraise substantial discoveries already made by major Australian oil and gas operators is ongoing
This ASX release has been authorised by the Managing Director, Alex Underwood
Registered Office Beetaloo Energy Australia Limited
Level 5, 6-10 O’Connell Street ABN 29 002 148 361
Sydney NSW 2000
Phone: +61 2 9251 1846 Securities Exchange
Facsimile: +61 4 9251 1022 ASX: BTL
Media and Investor Enquiries Share Registry
Nick Kell Computershare Investor Services
Phone +61 2 9251 1846 Phone: 1300 850 505
Beetaloo Energy Australia Limited www.beetalooenergy.com 4
ASX Listing Rule 5.30
(a) Name and type of well Carpentaria-5H, horizontal shale gas well
(b) Location of well and the details of the
permit or lease in which the well is located
Located in Beetaloo Energy’s wholly owned and operated EP187
tenement, located in the Beetaloo Sub-basin in the Northern
Territory
(c) The entity’s working interest in the well Beetaloo Energy holds a 100% working interest and operatorship
in Carpentaria-5H
(d) If the gross pay thickness is reported for an
interval of
conventional resources, the net pay
thickness
N/A
(e) Geological rock type of the formation drilled The horizontal section has been drilled in the B Shale of the
Velkerri Formation
(f) Depth of the zones tested The depths of the 2,955 metre (9,625 foot) fracture stimulated
horizontal section tested range from 1,626 to 1,595 metres
(5,007 feet to 5,233 feet) True Vertical Depth (TVD) referenced to
Rotary Table (7.2 metres (23.6 feet) above ground level). 2.955
metres (9,625 feet) of the 3,310 metres (10,860 feet) horizontal
section was fracture stimulated.
(g) Types of test undertaken and the duration
of the tests
Extended production testing following fracture stimulation.
The current 30-day (IP30) test period was preceded by ~74 days
of stimulation cleanup flow with gas breakthrough following the
fracture stimulation, The preceding period included a previously
announced 30-day cleanup test (Carpentaria-5H Clean-Up Flow
Test Update announcement on 22 December 2025)
(h) The hydrocarbon phases recovered in the
tests
High Calorific Gas –
C-5H Gas recovery - mole %: Methane 82.77, Ethane 12.25,
Propane 1.61, Butane 0.34, Pentane and Higher 0.09. Conversion
factor of raw MMSCF to TJ is 1.173
(i) Any other recovery, such as , formation
water and water, associated with the test(s)
and their respective proportions
Across all testing ~148,500 barrels of flowback fluid recovered,
representing 27.5% of total injected water. During the current
30-day test period, the rate of fluid flowback declined from
~1,300 bbl / day to ~440 bbl / day
(j) The choke size used, the flow rates and, if
measured, the volumes of the hydrocarbon
phases measured
Choke sizes were held between 56/64” to 80/64” following a
multi-day opening sequence over the IP30 period. Gas flow has
averaged 6.9 TJ / day (5.85 mmscf / day)
(k) If flow rates were tested, information about
the pressures
associated with the flow and the duration of
the test.
Wellhead pressure ranged from ~1,380 psig to ~240 psig. Test
duration 30-days (2:15pm 11 June 2026 to – 2:15 pm 11 July
2026)
(l) The number of fracture stimulation stages
and the size and nature of fracture
stimulation applied
67 slickwater stages along an effective stimulated horizontal
length of 2,955 metres (9,695 feet) executed with a total of
~11,000 tonnes of proppant (sand) placed representing an
average proppant intensity of 2,295 lb/ft
(m) Any material volumes of non-hydrocarbon
gases, such as, carbon dioxide, nitrogen,
hydrogen sulphide and sulphur.
Mole %: Helium 0.14%, Carbon Dioxide 0.84% and other Inert
volume 1.95%
(n) Any other information that is material to
understanding the reported results
Not applicable